On the 9th December 2019, the Mine Action Center carried out quality control of the works completed in the second phase of the Project for Demining-Clearance of Explosive Remnants of War from Jugovićevo-2 Site, No. 215/19, Novi Sad. The second phase included ERW search up to a 3 m depth.

  Quality control on Jugovićevo-2 project

Furthermore, the Contractor was introduced into works in accordance with the third phase of the Project, which includes ERW search up to an 18m depth.