MENU
Home » Quality control on project for search and excavation of ERW from Data centre construction site in Kragujevac
23.09.2019.
Quality control on project for search and excavation of ERW from Data centre construction site in Kragujevac
Оn 20th September 2019, the Mine Action Centre conducted quality control of the works performed on the part of leveled area of the Project for Search and Excavation of Explosive Remnants of War (ERW) from Data Centre Construction Site, Number 217/19, City of Kragujevac.
The analysis of data, which the Belgrade based Contractor Millennium Team obtained in the field using the devices equipped with a data logger, established that there are no ERWs or anomalies indicating the existence of an object of the mass within the limits of the critical error determined by this Project.