Quality Control in Accordance with UXO Clearance Project for EDePRO 1- C2 site
On April the 13th, 2022, as a follow up activity of the implementation of the UXO Clearance Project for EDePRO 1- C2 site, in the territory of the Municipality of Grocka - the outskirts of Leštane, the Serbian Mine Action Centre conducted quality control of the works in accordance with Phase 1 of the Project, namely on the area which the contractor searched up to a 50 cm depth, as well as on the area on which the contractor carried out a depth recording.
On this occasion, the control did not establish any critical errors defined by this Project.
The Contractor continues the works in coordination with SMAC.