Home » Quality Control in Accpordance with ERW Clearance Project for the Expressway - Ib of the state Road No. 21, Novi Sad - Ruma ,,Fruška Gora Corridor” Site
18.01.2022.
Quality Control in Accpordance with ERW Clearance Project for the Expressway - Ib of the state Road No. 21, Novi Sad - Ruma ,,Fruška Gora Corridor” Site
On Јаnuary the 18th, as a follow up activity of the implementation of the ERW Clearance Project for the Expressway - Ib of the state Road No. 21, Novi Sad – Ruma, “Fruška Gora Corridor” Site, the Serbian Mine Action Centre conducted quality control of the works in accordance with Phase 1 of the Project, namely on the area which the contractor searched up to a 50 cm depth, as well as on the area on which the contractor carried out a depth recording.
On this occasion, the control did not establish any critical errors defined by this Project.
The Contractor continues the works in coordination with SMAC.