Quality Control in Accordance with ERW Clearance Project for the Expressway - Ib of the state Road No. 21, Novi Sad - Ruma ,,Fruška Gora Corridor” Site
On December 7th 2021, as a follow up activity of the implementation of the ERW Clearance Project for the Expressway - Ib of the state Road No. 21, Novi Sad – Ruma, “Fruška Gora Corridor” Site, the Serbian Mine Action Centre conducted quality control of the works for the part of the site, which Contractor Millennium Team Ltd., carried out in accordance with SMAC’s project, International Mine Action Standards (IMAS) and Standard Operating Procedures.
The control was performed on the area which the contractor searched to a 50 cm depth.
On this occasion, the control did not establish any critical errors defined by this Project.
During the so far implementation of the works, the Contractor found 2 UXO.
The Contractor continues the works in coordination with SMAC.