 Quality control on Končulj – Transmission line 1 and 2 project  Quality control on Končulj – Transmission line 1 and 2 project

On the 23rd September 2021, as a part of follow up to the implementation of Demining Project of the Končulj Transmission Line 1 and 2 site, Bujanovac Municipality, Serbian Mine Action Center carried out quality control at a part of the site searched and demined by NGO Stop Mines, Pale, Republic of Srpska, Bosnia and Herzegovina., in accordance with the SMAC Project, International Mine Action Standards and Standard Operating Procedures.

Quality control was carried out by manual method and by the use of mine detection dogs (MDDs).

Critical errors determined by this Project have not been established.