Home » Quality control on ERW clearance project of areas in the zone of the bridge at Sremska Rača and along planned route of Belgrade - Sarajevo highway, Sremska Rača - Kuzmin section
02.04.2021.

Quality control on ERW clearance project of areas in the zone of the bridge at Sremska Rača and along
planned route of Belgrade - Sarajevo highway,
Sremska Rača - Kuzmin section

  Quality control on ERW clearance project of areas in the zone of the bridge at Sremska Rača and along planned route of Belgrade - Sarajevo highway, Sremska Rača - Kuzmin section

On April 2, 2021, SMAC representatives conducted quality control on the part of the ERW clearance project of areas in the zone of the bridge at Sremska Rača and along planned route of Belgrade - Sarajevo highway,Sremska Rača - Kuzmin section.

Within Phase 1 of this Project, "Millennium Team" Ltd., Belgrade and subcontractor "ARM Razminiranje" Ltd., Belgrade, searched and cleared the area to a depth of 50 cm.

  Quality control on ERW clearance project of areas in the zone of the bridge at Sremska Rača and along planned route of Belgrade - Sarajevo highway, Sremska Rača - Kuzmin section

Quality control has determined that there are no ERWs or anomalies that indicate the existence of an object of a mass within the critical error limits determined by the Project.

Thus, conditions for smooth implementation of the next phases in accordance with the Project have been created.