Home » Commencement of works according to Cluster Munitions Clearance Project "Constantine the Great Airport - 6th Phase" in Niš
04.03.2021.

Commencement of works according to Cluster
Munitions Clearance Project
"Constantine the Great Airport - 6th Phase"
in Niš

  Commencement of works according to Cluster Munitions Clearance Project Constantine the Great Airport - 6th Phase in Niš    Commencement of works according to Cluster Munitions Clearance Project Constantine the Great Airport - 6th Phase in Niš

On the 4th March 2021, with the introduction of selected contractor "Nucleus Team" Ltd., Belgrade, into works, commenced the implementation of Cluster Munitions Clearance Project for the site “Constantine the Great Airport – 6th Phase”, No. 0233/20, City of Niš.

The project was developed in accordance with the request of company "Airports of Serbia" Ltd., Niš, as an investor of works.

  Commencement of works according to Cluster Munitions Clearance Project Constantine the Great Airport - 6th Phase in Niš    Commencement of works according to Cluster Munitions Clearance Project Constantine the Great Airport - 6th Phase in Niš

The project site is located in the territory of the City of Niš, outside the complex of the Constantine the Great Airport, in the continuation of the approach lights.

The area to be cleared of cluster munitions and other ERW totals14,444 sqm.

  Commencement of works according to Cluster Munitions Clearance Project Constantine the Great Airport - 6th Phase in Niš    Commencement of works according to Cluster Munitions Clearance Project Constantine the Great Airport - 6th Phase in Niš

Upon completion of clearance of this site, danger posed by unexploded cluster munitions and other ERW will be removed and regular maintenance and execution of construction works will be enabled. This will contribute fully to the air traffic safety and further development of the Niš civil airport.